In addition to the deep experience team members have brought with them to Pacifico Power, the Pacifico Energy and Pacifico Power teams have completed, or have in development over 1 GW of solar projects.
Hosoe
Miyazaki | Japan
Offtaker of electricity
Kyushu Electric Power Company
Scale of power generation
96.2 MWdc
Location
Miyazaki-shi, Miyazaki-ken
EPC contractor
oyo Engineering Corp.
Project finance
MUFG Bank, Ltd., 10 Syndication Banks
Date of facility certification
January 25, 2013
Commencement of construction
March 2015
Date of commercial operation
February 19, 2018
Status
Operational