Iwaki
Fukushima, Japan
42.3
Offtaker of Electricity
Tohoku Electric Power CompanyScale of Power Generation
42.3 MWdcLocation
Iwaki-shi, Fukushima-kenEPC Contractor
Toyo Engineering Corp.Project Finance
Shinsei Bank, Ltd.Date of Facility Certification
March 28, 2014Commencement of Construction
September 2017Date of Commercial Operation
April 13, 2020Status
Operational