Iwaki

Fukushima, Japan

42.3

One of the most difficult projects developed and constructed, Iwaki involved the coordination of multiple landowners across its relatively steep slopes, measuring up to 20 degrees.

Iwaki

Fukushima, Japan

42.3

Offtaker of Electricity

Tohoku Electric Power Company

Scale of Power Generation

42.3 MWdc

Location

Iwaki-shi, Fukushima-ken

EPC Contractor

Toyo Engineering Corp.

Project Finance

Shinsei Bank, Ltd.

Date of Facility Certification

March 28, 2014

Commencement of Construction

September 2017

Date of Commercial Operation

April 13, 2020

Status

Operational
Projects
ENERGY AS A SERVICE : BUILD WITH PACIFICO POWER