Mimasaka
Okayama, Japan
42
Offtaker of Electricity
Chugoku Electric Power CompanyScale of Power Generation
42 MWdcLocation
Mimasaka-shi, Okayama-kenEPC Contractor
Toyo Engineering Corp.Project Finance
MUFG Bank, Ltd.The Chugoku Bank, Ltd.
Date of Facility Certification
December 11, 2012Commencement of Construction
December 2014Date of Commercial Operation
July 1, 2016Status
Operational